Dependent tasks start two days after end of precedent task

description

If two tasks are related tasks, the dependent tasks start two days after end of precedent task

file attachments

comments

JacobChrist wrote Jul 17, 2015 at 2:22 AM

Attached is an image showing issue.

jakesee wrote Jul 18, 2015 at 8:06 AM

Hi JacobChrist,

The in the image you attached, the precedent "Master Mix" task ends on 30th and the following "Sample Transfer" task starts on the 31, so it is only 1 day -- i.e. it starts on the next day.

As I have mentioned, unfortunately, the control current has a smaller resolution of 1 day. Hence the dependent task must start on the next day.