Request: How to change business working days on gantt chart area

description

Dear friends,
I've a question, how to change business working days on _mchart area, I mean the hashed columns which appears at (Saturday and Sunday), How to make it appears for (Friday and Saturday) ??
More clarification: I want weekly working days to be starting from (Sunday) till (Thursday) and weekend days to be (Friday and Saturday).

Thanks for your support in advance ;)

comments

jakesee wrote Jun 21, 2014 at 7:04 AM

Hi,

Please find the line
if (date.DayOfWeek == DayOfWeek.Sunday || date.DayOfWeek == DayOfWeek.Saturday)
in Chart.cs file and change Sunday to Friday.

Thanks!

midogates wrote Jun 21, 2014 at 7:27 AM

It works 100%

Many Thanks for your usual support :)